Hamedan project porgress
Description
The plan of ethylene oxide production plant and its downstream units in Hamedan, was proposed based on the petrochemical industries development committee in order to replace with vinyl acetate monomer (VAM) in Hamadan. After technical and economic studies, market demands and multiple meetings with relevant experts, this project was approved by the National Petrochemical Company board of directors. In this regard, Ibn Sina Petrochemical Company (PJSC.) was established for the plant performance and operation with the participation of the private sector
Ibn Sina Petrochemical Complex including various units of ethylene oxide, ethanol amine, Methyl di ethanol amine, glycol ether and is ethoxylates
:All activities related to the project are in two parts Non-EPC and EPC. The main mentioned topics are listed as follows
Documents
Project Progress
14%
Project Time
- Start
Mar 21 2015
- End
Mar 19 2020
Stages of completion of projects
-
25%
-
75%
14%
-
50%
Non-EPC completed 45%
Description
Separate sections related to the Non-EPC include:
1. Land
1.1 purchase and land ownership
1.2 Land preparation
2. basic engineering and license
2.1 Research and data collection for basic design
2.2-Obtaining the license and basic design documents
3. Supply Utility
3.1 Water Supply
3.2-Power supply
3.3-Gas supply
4. Feed supply from West Ethylene pipe line
5. Bank loans
EPC completed 0%
Description
Separate sections related to the EPC include:
1. Detailed Engineering
2. Procurement
3. Equipment construction and installation
4. Set up